Project Overview
Phase 2, Unit B at Greenogue Logistics Park involved the fit-out of a 90,000 sq ft warehouse facility for Wincanton and IKEA. The works were delivered as a focused, fast-track package designed to support high-volume logistics operations within an operational distribution environment.
The scope centred on installing specialist racking, fire protection systems and upgraded lighting to enable immediate operational use while maintaining compliance with fire and safety standards.
Project Requirements
The client required a rapid and efficient fit-out solution to support logistics operations within a tight programme. Key requirements included the installation of high-density racking systems, integration of roof-level and in-rack sprinkler protection, and enhancements to lighting and fire alarm systems, all delivered with minimal disruption to surrounding activities.
The project also required close coordination between design, construction and specialist contractors to ensure safe delivery within an operational warehouse setting.
Glencar’s Role
Glencar was appointed to deliver the Phase 2 fit-out works, coordinating specialist subcontractors and managing programme, safety and quality throughout the works. The team ensured seamless integration of racking, sprinkler and electrical systems to meet operational and compliance requirements.
Scope of Works
Warehouse Fit-Out
- Installation of specialist warehouse racking systems
- Coordination with operational layout and logistics requirements
Fire Protection Systems
- Installation of roof-level sprinkler systems
- Installation of in-rack sprinkler protection
- Integration with existing fire alarm systems
Electrical & Lighting
- Installation of additional internal lighting
- Fire alarm system enhancements to support operational use
Technical & Delivery Challenges
The key challenge was delivering a technically complex fit-out package within a compressed 12-week programme. Coordinating racking installation alongside sprinkler and lighting systems required detailed sequencing to avoid clashes and ensure compliance with fire strategy requirements.
Working within an active logistics environment demanded strict safety controls and clear communication to maintain uninterrupted operations.
Delivery Conditions Addressed
- Live logistics environment
- Tight programme constraints
- Specialist racking and fire protection systems
- Multi-discipline coordination
- Safety-critical installation sequencing
The Outcome
Phase 2, Unit B at Greenogue Logistics Park was successfully delivered within programme, providing Wincanton and IKEA with an enhanced, fully operational warehouse facility. The completed fit-out supports efficient, safe and compliant logistics operations within a modern distribution environment.
Sector
Completed
Programme
Architect