Glencar starts piling on final build phase of Pure DC’s £1bn+ Brent Cross data centre campus
2nd September 2026
Piling Underway at Pure DC’s LON01B2
The milestone moves the Brent Cross development into its structural phase, with Glencar delivering the West Cold Shell within a live operational campus. Once complete, LON01B2 will support the expansion of the site to 90MW and form part of a next-generation, liquid-cooled data centre designed for high-density AI and cloud workloads.
Glencar has commenced piling works for the West Shell of Pure Data Centres’ (Pure DC) 70MW LON01B2 facility, marking the start of the final major build phase at its £1bn+ Brent Cross Data Centre campus in North London.
The development will extend the campus by more than 23,000 sq. m and, once complete, bring total capacity to 90MW. Completion of B2 is scheduled for Q2 2029.
Glencar’s scope includes delivery of the West Cold Shell, incorporating piling and foundations, underground services and associated works, structural frame and connections to the adjacent East Cold Shell, concrete and slab works, stair cores, building envelope and roofing.
The project is being delivered within a live operational data centre campus, requiring close coordination between Glencar, Pure DC and the wider project team as multiple construction and fit-out activities progress simultaneously across the development.
LON01 is being developed as a next-generation, closed-loop, liquid-cooled data centre capable of supporting high-density AI inference and cloud workloads. Designed for long-term resilience, the campus incorporates sustainability measures including recycled steel and low-carbon components.
Following completion of B2, the site will also be home to one of the world’s largest living walls. More than 750,000 plants will wrap around the building, helping to reduce noise and air pollution while creating habitat for insects and birds adjacent to the Brent Reservoir Site of Special Scientific Interest (SSSI).
Representatives from Pure DC and Glencar joined the project team on site to mark commencement of piling and the transition into the structural phase of the programme.
Dan Priest
Campus Delivery Director at Pure DC
Roy Jones
Managing Director of London and The South at Glencar
“Our teams have worked closely with Pure DC and the wider project team to prepare for this phase. LON01B2 further demonstrates Glencar’s capability to deliver complex, mission-critical infrastructure within live operational environments, and we look forward to building on this momentum as the structure begins to take shape.